Updated November 20, 2026 · ElectricService101 Editorial Team · 9 min read

Quick answer

An underground residential service runs in buried conduit from the utility's pad-mount transformer or pedestal to a meter base on the house. Bury PVC conduit at least 18 inches deep under the NEC, or deeper if your utility requires it (30 to 36 inches is common). Use long-radius sweeps, a Schedule 80 or rigid metal riser with an expansion fitting, and warning tape 12 inches above the conduit.

Utility side (typical) Customer side (typical) Service point (set by utility) Grade Pad-mount transformer Service lateral in PVC conduit 18 in. NEC minimum cover; utilities often require 30 in. or more House wall Sch. 80 riser + expansion fitting Meter-main meter + outdoor disconnect Panel Inside Ground rods
Typical underground residential service. Where ownership changes, conduit depth, and who pulls the wire vary by utility.

How deep must an underground service be buried?

NEC Table 300.5 sets minimum cover, measured from the top of the conduit or cable to finished grade. Your utility's handbook can, and often does, require more.

Wiring methodNEC minimum cover
Rigid PVC conduit18 in.
Direct-burial cable (USE, URD)24 in.
Rigid metal conduit (RMC) or IMC6 in.
Utility requirement, AEP Ohio (example)30 in.

What conduit should you use?

Gray Schedule 40 PVC electrical conduit is the standard choice underground. Use Schedule 80 PVC or rigid metal conduit for the exposed riser. Size the conduit to your utility's specification, commonly 2 to 3 inches for a 200-amp service, and use factory long-radius sweeps (24- or 36-inch radius) so heavy aluminum cable pulls without damage.

Step by step: installing the service lateral

  1. Apply to your utility: Request service and get the utility's service requirements, the transformer location and the service point.
  2. Call 811: Have existing utilities marked at least a few business days before you dig.
  3. Pull permits: An electrical permit covers the meter base, riser and grounding. Some utilities also inspect the open trench.
  4. Dig the trench: Dig to the greater of the NEC minimum and your utility's depth, with a straight route and no sharp changes in grade.
  5. Lay conduit and sweeps: Glue PVC joints with solvent cement, use long-radius sweeps at each end, and keep total bends to 360 degrees or less between pull points.
  6. Install the riser: Run Schedule 80 PVC or rigid metal up the wall to the meter base, with an expansion fitting where required.
  7. Inspect, then backfill: Get the trench inspected if required, lay warning tape about 12 inches above the conduit, and backfill without rocks.
  8. Pull conductors: The utility or your electrician pulls the lateral and lands it in the meter base. Leave a pull string in place if the utility pulls its own cable.

Safety: never open, dig at or work inside a utility transformer or pedestal. Only the utility connects to the transformer. Service conductors upstream of the meter have no overcurrent protection.

What happens at the meter base?

The lateral enters the bottom of the meter base, often through a concentric knockout, and lands on the line-side lugs. If you have a separate main disconnect, the 2026 NEC now requires it outdoors. See our meter base guide, the wire size chart and the full parts list.

Frequently asked questions

What size conduit is used for a 200 amp underground service?

Utilities commonly specify 2-inch or 3-inch Schedule 40 PVC for a 200-amp residential lateral, and 3-inch or larger for 400-amp services. AEP's meter socket specification, for example, calls for knockouts sized for 3-inch conduit. Always use the size your utility requires, because it may pull its own cable through your conduit.

Do I need Schedule 80 PVC for the riser?

Use Schedule 80 PVC, or rigid metal conduit, where the conduit is exposed to physical damage, which includes the riser on the outside wall where it can be hit by mowers or vehicles. Many utilities require Schedule 80 or rigid metal for the riser even when Schedule 40 is used underground.

Why do underground service risers need an expansion fitting?

Soil settles and freezes, and PVC expands with temperature. Without room to move, the riser can pull the meter base off the wall or crack. NEC 300.5(J) requires allowance for earth movement, and many utilities require a slip-type expansion fitting on the riser below the meter base.

Is warning tape required over an underground service?

Yes. NEC 300.5(D)(3) requires a warning ribbon at least 12 inches above underground service conductors that are not encased in concrete and are buried 18 inches or more. Lay it in the trench as you backfill.

Sources: NFPA 70 (NEC) Table 300.5, 300.5(D)(3), 300.5(J), 352.26; AEP, Guide for Electric Service and Meter Installations (2026).